Remodeling Permits in Virginia Beach: Do You Need One?
Remodeling permits in Virginia Beach follow Virginia's Uniform Statewide Building Code. In short: removing or adding a wall, or changing plumbing, electrical wiring or mechanical systems, needs a permit. Replacing cabinets, trim, floor finishes and paint, and swapping fixtures without changing the pipes or wires behind them, generally doesn't (Virginia USBC, 13VAC5-63-80).
Most bigger remodels include at least some permitted work. When we take on home remodeling in Virginia Beach, we handle the permit process for you. This guide explains how the rules break down so you know what to expect.
What remodeling work needs a permit in Virginia?
Section 108 of the state building code says a permit has to be obtained before starting certain work. For homeowners, the items that come up most in a remodel are:
Removing or adding any wall, partition or part of one. That covers opening up a kitchen, combining rooms or framing a new room.
Work on the water supply, drain or vent piping. Moving a sink, a toilet or a shower drain falls here.
Electrical wiring. New circuits and moved outlets or lights are wiring work.
Mechanical, fire protection and fuel supply systems, such as ductwork and gas lines.
The code also notes that separate or combined permits may be required for building, plumbing, electrical and mechanical work (Virginia USBC, 13VAC5-63-100). A larger remodel can involve more than one.
What doesn't need a permit?
The same section lists "ordinary repairs" that don't need a permit or inspections. The ones homeowners ask about most:
Installing or replacing cabinetry or trim. Installing or replacing floor finishes. Painting and wallpaper.
Replacing plumbing fixtures, as long as the water supply, drain and vent systems aren't altered. A new faucet or toilet in the same spot is usually a fixture swap.
Replacing windows and doors with ones of similar operation and size, where the framed opening doesn't change.
Replacing standard switches and receptacles in single-family homes.
Some roofing work: the code exempts replacing roof covering on one- and two-family homes within its wind-speed limits, and small areas of roof decking.
Two cautions. The exemption doesn't excuse the work from the rest of the code; it still has to be done right. And in a historic district or a special flood hazard area, a permit may be required even for some of these items. If you're not sure, ask before you start.
Who gets the permit, the homeowner or the contractor?
The code allows the owner, a tenant, either one's agent, or the contractor or subcontractor doing the work to apply. Anyone applying for construction work has to show they're a licensed contractor, or state in writing that they aren't required to be one.
On our jobs, we handle it. We're a Virginia Class A residential building contractor, and we're familiar with the permit process. We often work with architects and engineers as well as the permit office when a project needs drawings.
Does a permit slow my remodel down?
In our experience, the permit itself usually doesn't slow a job down much. The bigger delays come from surprises inside the walls and changes made after work starts.
What matters is timing. A permit has to be approved before the work that needs it can begin, so we build it into the schedule. Before we start, the permit is approved, the design decisions are made and the plan is set.
What about older homes?
Older homes bring more permitted work, because so much of what's behind the walls needs updating. About two-thirds of Norfolk's homes and about four in ten of Virginia Beach's were built before 1980 (U.S. Census Bureau, 2024 ACS). When we open a wall in a house that age, the wiring or plumbing we touch often has to be brought up to today's code.
That's one reason we ask how old your house is on the very first call. It helps us plan for the permits and inspections the job is likely to need.
Do inspections happen too?
Yes. Work done under a permit is inspected before the job is closed out. We build the inspections into the schedule so they happen at the right time and the job keeps moving, instead of stopping to wait.
What's the next step?
If you're planning a remodel and wondering what permits it will need, call (757) 563-3375. We'll look at the project, tell you what's likely to need a permit and include it in your estimate. Every project comes with a one-year warranty on workmanship and materials.